Roads, transportation & public access
Active and upcoming changes, plus recent water-quality results. Older or additional notices are left out.
Roads
Caltrans is scheduled to begin one-way traffic control on the Lagunitas Creek Bridge Replacement Project on State Route 1 (Shoreline Highway) on Monday, Aug. 10. Traffic control will be in place from August until November 2026. Once work begins, the trailhead to Papermill Creek Trail near the bridge will be closed for the safety of residents and crews. The full closure of the bridge is scheduled for after Labor Day weekend in September 2027.
Upcoming — begins Aug. 10, 2026 · Caltrans · Jul. 29, 2026
Current-condition checks
County roads: The County map listed no active West Marin road closure. Open official source Checked Aug. 3, 2026
State Route 1: Caltrans listed no current State Route 1 restriction in Marin County. Open official source Checked Aug. 3, 2026
Marin Transit routes 61/68: Marin Transit listed no current service change for routes 61 or 68. Open official source Checked Aug. 3, 2026
Point Reyes National Seashore: The National Park Service listed no new active Point Reyes alert. Open official source Checked Aug. 3, 2026
Critical project watch
Projects officers have asked to keep in view. Each status includes the date it was last confirmed.
Critical watch · Point Reyes
Point Reyes gas-station redevelopment
11401 State Route 1, Point Reyes Station
Building permit pending
Latest known status · Jul. 23, 2026
Planning approval was reported complete in November 2024. A building-permit application was received Sept. 17, 2025; the live County feed shows no issued date and no inspection.
Tracking ID 93556 · APN 119-198-03 · Open County permit table — then search 93556
Convert the existing building into five apartments and a retail store. The County building-permit record lists an estimated construction value of $1.2 million.
Sources: Live County permit and inspection feeds, supplemented by dated local reporting.
What to watch
No hearing or inspection date listed: The permit and inspection feeds list no hearing, issuance or inspection date. Recheck the County table — search 93556
Next update to watch for: Permit issuance, a revised or ended application, or the first inspection.
Recent project coverage
Oct. 22, 2025 · Point Reyes Light · New gas station operator takes over in Point Reyes
Aug. 27, 2025 · Point Reyes Light · Redwood Oil keeps Point Reyes store, sells others
Critical watch · Point Reyes
Grandi Building hotel and restaurant renovation
11101 State Route 1, Point Reyes Station
Planning approvals granted
Latest known status · Jul. 25, 2026
The Deputy Zoning Administrator approved coastal development, master use and design-review permits on April 9, 2026. The County also gave preliminary approval, with conditions, to the proposed septic system. The building-permit feed checked July 25 showed no renovation permit for the site.
Planning case P5581 · APN 119-234-01 · Open official County project page — P5581
Restore and adapt the historic Grandi Building as a 34-room hotel, 60-seat restaurant and 400-square-foot retail space, with two employee apartments in an adjacent storage building and a new onsite wastewater system.
Sources: Official County project page and adopted resolution, live County building-permit feed, and dated local reporting.
What to watch
Planning approvals granted April 9: The County approved the coastal development permit, master use permit and design review. The septic proposal received preliminary approval with conditions. Open County project page — P5581
What to watch next: Final wastewater clearances, a renovation building-permit application or issuance, and the start of construction. No future hearing date was found.
Recent project coverage
Apr. 15, 2026 · Point Reyes Light · Grandi owner secures permit for renovation
Jul. 23, 2025 · Point Reyes Light · Grandi owner revives hotel, restaurant plan
Critical watch · Point Reyes
Lagunitas Creek (Green) Bridge replacement
State Route 1 just south of Point Reyes Station
Construction phase
Latest known status · Jul. 29, 2026
Caltrans lists the project in its construction phase. One-way traffic control is scheduled to begin Aug. 10, 2026 and continue through November. A 21-day full closure of the bridge is targeted for after Labor Day weekend in September 2027.
Caltrans District 4 · Lagunitas Creek Bridge Project · Open the official Caltrans project page
Replace the 1929 bridge, widen the culvert to the north, add wider shoulders, ADA-compliant sidewalk and curb ramps, and add a crosswalk at Sir Francis Drake Boulevard. The Papermill Creek Trail entrance near the bridge will close when work begins; the C Street entrance will remain open.
Sources: Official Caltrans District 4 project page and July 29 traffic advisory.
What to watch
One-way traffic control begins Aug. 10: A temporary signal will alternate traffic through the work zone. Caltrans expects one-way control from August through November 2026. Open the Caltrans advisory
Trail access changes when work begins: The Papermill Creek Trail entrance near the bridge will close; the C Street entrance will remain open.
Full closure targeted for September 2027: Caltrans says a 21-day full bridge closure is targeted for after Labor Day weekend in September 2027. Exact dates have not been announced.
Project completion targeted for summer 2028: The schedule includes winter suspension, construction resuming in spring 2027 and plant-establishment work through summer 2028.
Recent project coverage
Jan. 14, 2026 · Point Reyes Light · North Marin wraps up water line work ahead of Green Bridge replacement
Dec. 22, 2025 · Point Reyes Light · Funds awarded to cover Green Bridge replacement
Critical watch · Point Reyes
Point Reyes 67-lot subdivision proposal
Point Reyes Station · APNs 119-050-04, 119-050-09, 119-140-03 and 119-140-09
Application withdrawn
Latest known status · Apr. 29, 2026
The developer withdrew the application while the County considers coastal-development rule changes, according to the Point Reyes Light. The site remains on the watchlist for a possible refiling.
Planning case P5033 · Read the latest status report
The withdrawn proposal covered 82.32 acres and 67 lots: 61 market-rate single-family parcels, three parcels designated for 22 affordable units, two wetland-preservation parcels, roads, stormwater facilities and community wastewater systems.
Sources: April 29 Point Reyes Light status report, checked against an older archived County project page.
What to watch
No active hearing or deadline found: The application was reported withdrawn, so no project hearing or comment deadline is currently listed in the sources checked.
Next update to watch for: A new or refiled application, or a County decision changing the coastal rules that prompted the pause. No date has been announced. Background on the pause
Recent project coverage
Apr. 29, 2026 · Point Reyes Light · Point Reyes subdivision plan paused
Jan. 7, 2026 · Point Reyes Light · Third try for subdivision proposal
Regional high-impact watch
Large Tomales agricultural development proposal
28200 State Route 1, Tomales
Application incomplete
Latest known status · Feb. 6, 2026
Incomplete on the latest accessible archived County project page.
Planning case P6126 · Open archived official County page
Approximately 42,085 square feet of proposed development, including a 7,480-square-foot farmhouse, equipment barn, stable, corral, two agricultural-worker housing units, road improvements and a new septic system.
Sources: Archived official County page; current live status has not been independently confirmed.
What to watch
No public hearing date found: The cited County page lists the application as incomplete and does not show a hearing, comment deadline or decision date.
Next update to watch for: Submission of missing material followed by a County completeness determination. Environmental and coastal review may follow if the application advances; no date is published.
Recent project coverage
No clearly project-specific article was found in the current searches.