Current watch status

  • Building permit pending: Point Reyes gas-station redevelopment - Open County permit table — then search 93556
    Planning approval is complete, but building-permit tracking ID 93556 still has no issued date and no inspection posted.

  • Planning approvals granted: Grandi Building hotel and restaurant renovation - no renovation permit for the site
    County planning approvals were granted April 9 for a hotel, restaurant, retail space and two employee apartments; no renovation building permit was found in the County feed checked July 25.

  • Construction phase: Lagunitas Creek (Green) Bridge replacement - Open the official Caltrans project page
    Caltrans' July 29 advisory scheduled one-way traffic control for August–November 2026. Its current highway feed listed no Marin restriction when checked Oct. 26; that does not confirm the scheduled work was canceled. A 21-day closure remains targeted for September 2027.

  • Final Funding Secured: Point Reyes Coast Guard Affordable Housing - Open the official County project page
    The 54-home redevelopment secured its final $27 million in tax credits; construction must begin by the end of 2026, and completion is required by Dec. 31, 2028.

  • Application incomplete: Large Tomales agricultural development proposal - Open archived official county page
    The latest accessible County project page lists the application as incomplete; no hearing or decision date was found.

  • Application withdrawn: Point Reyes 67-lot subdivision proposal - no permit for the site
    The developer withdrew the 67-lot application; the site remains on watch for a new filing or a related County coastal-rule decision.